King’s School Retaining Walls

COMPLETION
2024

LOCATION
King’s School

DURATION
4 Months

SCOPE
Retaining Walls , Earthworks

Retaining Walls & Earthworks 

Following the 2023 Auckland Anniversary floods, we worked with Oxcon CLL to remediate a failed retaining wall at King’s School. Works included removing 4,500m³ of earth, installing new piling, concrete walers, ground anchors, and upgraded drainage. Excavated material was stabilised and reused to restore the field, alongside a new timber wall on the south side to increase usable space. The project required careful delivery within an active school environment, close to a Significant Ecological Area, and under tight space constraints..